Client: Schollglas Group
Implementation period: 2018/2019
The project included:
Dismantling, transfer and re-installation of 8 production lines, comprising about 30 unit, plus a 30-ton main furnace
Refurbishment, cleaning and renovation of equipment
Pre-commissioning preparations of the lines.
This was a relocation project implemented in-production, with the plant of origin successively shut down while the plant of destination was preparing for commissioning. The project was completed in seven weeks.